Project Implementation Progress 2013

Here we invite you to follow the latest on the project implementation. The material is sorted, newest at the top of the page.


2nd Oct 2013, Wk 40


13w40-PP_IMG_5156.JPG

 

 Left we see the work on the road pavement.

 It changes the way the compound looks.

 

 

 

 Below:

 The work on the main hall continues...

  

13w40-PP_IMG_5160.JPG  13w40-PP_IMG_5163.JPG

We are filling the foundation of the dining rooms (they are on the outer circle of the main hall) with murram. For this purpose we had to buy a compacting machine.

13w40-PP_IMG_5170.JPG  13w40-PP_IMG_5172.JPG

Main-Hall from behind

13w40-PP_IMG_5178.JPG  13w40-PP_IMG_5182.JPG

13w40-PP_IMG_5185.JPG  13w40-PP_IMG_5187.JPG

13w40-PP_IMG_5191.JPG  13w40-PP_IMG_5193.JPG

 


19 Jul 2012, Wk29

After some (lots) finishing touches we have roofed the second primary school block .

Now we are continuing on the Main Hall which we hope to have roofed before the year-ends.

13w29-PP_AirView.jpg  Kissa's team at work

13w29-PP_IMG_5123.JPG  13w29-PP_IMG_5127.JPG

13w29-PP_IMG_5131.JPG  13w29-PP_IMG_5133.JPG

13w29-PP_IMG_5136.JPG

 Above and left we see the work as it is progressing on the Main-Hall.

 

Below left we see the  work on the roads going on. Soon all around the school will be paved with cement pavers.

 

 Below-right are the metal workers working on all the loose ends that need to be welded together.

 

 

13w29-PP_IMG_5141.JPG 13w29-PP_IMG_5147.JPG