Project Implementation Progress 2007

Here we invite you to follow the latest on the project implementation. The material is sorted, newest at the top of the page.


progress_2007-12-22_IMG_3975.JPG

Dec 22, 2007

 

Yesterday we connected the water- tank.

It was a pleasure to see the villagers coming from far with their 20 Ltr jarricans. We found out that water is a REAL BIG problem in th area!

What a blessing to provide safe drinking water for this village.

Merry Christmas Osia!

In the background you can see the roofwork for the first dormitory block that is going to function as mini-classrooms for the beginning.

 


progress_2007-12-10_IMG_3959.JPG

 

Dec 10, 2007

 

Today we have made a start on the roof-work.

 

Here, the boys are making a sample truss.

This will be used to replicate all the trusses.

Then we hope to put on the puttins,

followed by the roof-tiles

 

 

 

 

 


progress_2007-12-04_IMG_3954.JPG

December 4, 2007

The dormitory is growing by the day. Grace is making an inspection...


progress_2007-11-28_IMG_3939.JPGNovember 28, 2007

Isaak, the welder has begun work on site.

 

 

There is LOTs of work waiting for him to do.

 

 

 

progress_2007-11-28_IMG_3941.JPG

 

 

Cor proudly shows the work in progress. Things are moving well!

 

 

 

 

 

 


progress_2007-11-10_IMG_3890.JPG

November 10, 2007

 

 

Today we have installed the electric pump for our borehole.

What a blessing!

 

 

 

 


progress_2007-11-02_IMG_3888.JPG

November 2nd, 2007 progress_2007-11-02_IMG_3889.JPG

 

 

 

 

 

 

 

 

 

The dormitory is beginning to take shape.

At the same time we are working on the boundary wall with our (not too friendly) neighbors.

 


August 16, 2007
progress_2007-08-16_DSCF0564.JPG

 

Matthias Weigele with his wife-to-be Dagmar are the first to arrive of the German team to help build the first dormitory block.

Matthias and Dagmar plant a tree at the entrance of the compound.

progress_2007-08-18_IMG_7861.JPG

 

 

 

Aug 18, 2007

When the other members arrive they immediately go to work on the concrete slap for the first block.

Herman cannot be stopped!!

progress_2007-08-20_IMG_7884.JPG

 

 

Aug 20, 2007

Soon the first corner is seen coming up.

 

The team is determined to get the walls up before they leave...

progress_2007-08-23_DSC07897.JPG

 

 

August 23, 2007

 

A team photo to crown it all

 

Thank you all for a job well done!

 

 

 


progress_2007-08-07_IMG_3767.JPG August 7, 2007

 

Left:
The foundation of the first block of 4 rooms is almost done.

Down:

The shape of the first dormitory is coming together.

progress_2007-08-07_IMG_3768.JPG

 


progress_2007-08-01_IMG_3753.JPG

August 1st, 2007

 

Cor & Grace have the honor to lay the first brick for the very first building at the Osia site.

 

We prayed together with the Go-Team and dedicated the whole project to the Glory of the Lord Jesus Christ!

 

 

 

 

 

 


progress_2007-07-30_IMG_3722.JPG

July 30th, 2007

 

The visiting Go-Team of YWAM Holland is helping with the setting of the foundation of the first dormitory.

 

They also did a prayer-walk around the land

 

 

 


progress_2007-05-02_IMG_3592.JPG

May 2nd, 2007

 

This day the "Draco" drilling company came to start drilling the borehole.

 

At the end they did a test and found it can give more than 20 tonnes / Hr

 

Thank you Lord!

 

 


progress_2007-03-31_IMG_3548.JPG

March 31, 2007

 

You are looking at the wall that is being built at the driveway. This is the private road that we had to buy to give us access to the main Highway. (Bugiri to Malaba, Kenya)

 

The driveway is ~100 meters long

 

 

 

 

 

 


progress_2007-03-18_IMG_3452.JPG

March 18, 2007

 

 

Two containers are bought and transported to the Osia site.

 

They will serve as the workshop & store for the construction site